BlogProgramme & Planning

Fit-Out Programme Template - MS Project, Asta & P6 Export

A fit-out programme is not a generic construction programme. Cat A, Cat B, retail, healthcare, data centre - each has its own trade sequence, lead times, regulatory hold points and handover requirements. A generic MS Project template built from a civil engineering model will not sequence fit-out trades correctly and will not know what a Cat B strip-back or M&E first-fix sequence looks like.

28 March 2026·7 min read·Programme & Planning

The programme is the most commercially critical document on a fit-out project. It governs when trades start, when materials need to be on site, when inspections need to be booked and when the client can take occupation. A programme that is wrong at the start - because it was built from an inappropriate template - will be wrong every week thereafter, and the cost of recovery compounds.

Under JCT Design and Build or NEC4 ECC, the contractor's programme has contractual status. A properly structured programme with CPM critical path, realistic float and correct trade sequencing is your first line of defence in any programme-related dispute. It is also the document your client's project manager will scrutinise most closely at every progress review. Getting it right from the outset is not optional on any project above Cat B fit-out.

What a complete Cat B fit-out programme must include

A credible Cat B fit-out programme covers the full project lifecycle from pre-construction through CDM handover. The following activities must be present, sequenced and linked with correct dependencies.

Programme checklist - Cat B fit-out
  • RIBA Stage and tender / pre-construction activities
  • Enabling and strip-out works
  • Structural / builders’ work sequence
  • M&E first fix (mechanical then electrical sequence)
  • Dry lining and partitions
  • M&E second fix
  • Ceiling grid and tiles
  • Floor finishes (sequenced by area)
  • Joinery and fit-out (comms room, kitchen, WCs)
  • IT / AV / data installation
  • Snagging and defects
  • Phased handover by floor / zone if applicable
  • Practical completion and client walkthrough
  • CDM handover documentation

On multi-floor or phased projects, each zone should be sequenced independently with inter-zone dependencies modelled correctly. A programme that rolls all floors into a single set of activities will mask slippage until it is too late to recover.

Why generic MS Project templates fail on fit-out

There are hundreds of generic MS Project templates available as free downloads. Most are built around civil engineering or structural construction workflows. The following are the consistent failure points when they are applied to fit-out programmes.

No fit-out trade logic

Civil engineering templates sequence earthworks, structural, civil finishes. A Cat B office fit-out sequences differently: M&E first fix must precede dry lining, ceiling grids cannot follow until M&E second fix is signed off, floor finishes are typically the last trade in each zone. A civil template applied to a fit-out programme will produce an illogical sequence that site teams will immediately discard.

No RIBA stages or pre-construction activities

A fit-out programme does not start on site. Tender review, scope freeze, specialist procurement, building control applications, landlord approvals, CDM pre-construction phase - all of these have lead times and dependencies that a generic construction template omits entirely. Missing pre-construction logic means your programme will be wrong before a single operative sets foot on site.

No dependency logic between M&E and dry-lining

The M&E / dry-lining interface is the most common cause of programme slippage on Cat B fit-outs. Partitions cannot be boarded until first-fix sign-off. Ceiling tiles cannot be fixed until second-fix is complete. Generic templates do not model this dependency correctly, which means float is misrepresented and the critical path runs through the wrong activities.

Cannot export to Asta XML or P6 XER

MS Project .mpp files are not universally accepted. Main contractors on large schemes typically require Asta Powerproject XML for programme reviews. NEC4 projects under infrastructure frameworks commonly specify P6 XER. An MS Project template cannot produce either format. If your client or main contractor requires Asta or P6 submission, an MS Project template is the wrong starting point.

How FitOut Insider generates your fit-out programme

FitOut Insider's Programme Builder is built for fit-out and interior construction - not adapted from a civil engineering scheduler. Describe the project in plain English: Cat B office, three floors, 12 weeks, JCT D&B, phased handover by floor. The AI generates a complete programme with fit-out-specific trade sequencing built in.

What the tool produces
  • 60–120 tasks with correct fit-out trade sequencing and dependency logic
  • CPM critical path with total float and free float per activity
  • Earned Value Management (EVM) baseline - EV, PV, AC curves
  • Monte Carlo schedule risk analysis with P50 / P80 completion dates
  • MS Project XML export (.mpp compatible)
  • Asta Powerproject XML export
  • Primavera P6 XER export
  • PDF Gantt chart - print-ready for client programme reviews
  • Built-in RIBA stage logic for pre-construction and design activities

The tool is used by UK fit-out contractors, main contractors managing specialist packages, and QS firms preparing tender programmes. On Cat A shell-and-core projects, the same logic applies - the tool understands the distinction between Cat A, Cat B, shell-only and full M&E fit-out scope.

Generate a fit-out programme in under 60 seconds

CPM. EVM. Monte Carlo. Asta XML, P6 XER, MS Project export. Built for fit-out.

Generate your fit-out programme →
← NEC4 Early Warning NoticeAll posts →